The Glenamuck District Roads Scheme (GDRS) is included in the County Development Plan 2016-2022 as a six year road objective, and is further detailed in the Kilternan Glenamuck Local Area Plan 2013.
Environmental Impact Assessment Report (EIAR) was submitted to An Bórd Pleanála for approval on 15th March 2019. Compulsory Purchase Order (CPO) was published on 2nd April 2019. Both went out to public consultation - closing date for submissions was 16th May 2019. A total of 40 submissions were received and an oral hearing was held in the offices of An Bord Pleanála in September 2019. The CPO was approved by An Bord Pleanála in December 2019. Notice of the confirmation of the CPO was advertised in February 2020.
BAM Civil Ltd was appointed as the contractor for the construction of the GDRS on 19th March 2024. The construction phase of the scheme commenced in April 2024 with a proposed programme of two years.
For the latest progress, please see attached Information Leaflet
Glenamuck Park
Part 8 planning approval was received on 14/06/2021 and the report is available to view in the related documents section on this page. The associated earthworks will be carried out as part of the road scheme. Subject to availability of funding and after the road is completed, the Parks Department of dlr will complete the detailed park design including landscaping and planting.
The scheme in general includes the following main provisions:
- Glenamuck District Distributor Road (GDDR) - Primary Link Road - single carriageway from tie-in at Enniskerry Road to the tie-in at the Glenamuck Road East / Golf Lane Roundabout
- Glenamuck Link Distributor Road (GLDR) - Primary Link Road - single carriageway from tie-in at Enniskerry Road to GDDR
- Provision of necessary SUDS attenuation ponds