A person shall not carry out works in contravention of Part M of the Second Schedule to the Building Regulations 2000 or any conditions subject to which a Disability Access Certificate is granted (where a Disability Access Certificate is required). 

To avoid potentially expensive remedial work,  it would be considered good practice to apply for a DAC at the same time as a Fire Safety Certificate ((FSC) prior to submitting a commencement notice), therefore ensuring that the DAC and any conditions pertaining to it are set out prior to commencement of works.  

However, a DAC may be applied for after commencement notice, but in no case shall a building be opened, operated or occupied or permitted to do so unless a DAC has been granted or pending determination of an appeals process.

A commencement notice must be submitted between 14-28 days in advance of work commencing.