Deansgrange Cycle Route Scheme

Project Updates

Friday, 5th July 2024:

Deansgrange road images showing work elements completed

We would like to thank the public for their patience and cooperation during these works. 

1. Works elements completed/ongoing:

  • The red cycle track tarmac on Kill Lane is complete.
  • Kerbing and paving are complete.
  • Line marking is 100% complete
  • The scheme is now substantially complete and operational.


2. Works lookahead (for July):

  • Install gates and railing for cemetery entrances
  • Install parking meter for businesses on Deansgrange Road
  • Install flexible bollards where required.
  • Continue snagging.
  • Remove the temporary works compound from the cemetery
  • Finish landscaping


3. Early warning items: None


4. Other:

There will be no further updates as the scheme is now substantially complete and operational. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 14th June 2024:

Deansgrange road images showing work elements completed

1. Works elements completed/ongoing:

  • Tarmacadam works at the junction of Kill Lane /  Deansgrange will be completed on 10th June and  11th June as scheduled.
  • The Tarmacadam base course for the red cycle track on Kill Lane is complete.
  • Commissioning of the new Toucan crossing and installation of  Smart Micro radars on Kill Lane took place on 6th June and 13th June. 
  • Kerbing and paving works on Kill Lane are complete.
  • Line marking is 50% complete.


2. Works lookahead:

  • Red-coloured tarmacadam for cycle tracks on Kill Lane will be laid next week  (10 am to 4 pm)
  • Gates and railing for cemeteries are being manufactured off-site.
  • Finish line marking. Install parking meter for businesses on Deansgrange Road.
  • Commence snagging.
  • Remove the temporary works compound from the cemetery. 

 

 3. Early warning items: None

 

4. Other:

Final update on Friday, 28th June 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

 

 

Friday, 31th May 2024:


Deansgrange road images showing work elements completed

 

1. Works elements completed/ongoing:

  • Brookville Park/ Springhill junction is 100% complete. Line marking and yellow box are in place.
  • Tarmacadam work at the junction of Deansgrange Road / St. Fintan’s Villas is complete. Line marking and yellow box are in place.
  • Wiring and ducting for traffic signal poles at Kill Lane/ Deansgrange Road junction was completed on 30 May.  
  • Traffic light poles for a toucan crossing at Clonkeen Park were erected.
  • Kerbing and paving works on Kill Lane are ongoing.


2. Works lookahead:

  • New public lighting to be switched on at the Northern Cemetery Entrance
  • Tarmacadam work for Kill Lane Deansgrange road junction  is scheduled for June 10th to June 12th  (Evening time work )
  • Commissioning the new Toucan crossing and installing Smart Micro radars on Kill Lane is scheduled for Thursday 6th June. Traffic Light switch out required from 10 am to 4 pm. The junction will be operated by Stop/ Go temporary traffic management.
  • Gates and railing for cemeteries are being manufactured off-site.
  • Commence snagging.


3. Early warning items:

  • The Junction of Kill Lane / Deansgrange Road is scheduled for resurfacing from Monday 10th June to  Wednesday 12th  June.  This will be evening time work. From 19:30 to midnight.


4. Other:

Next update is on Friday, 14th June 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

Traffic Alert: Thursday 30th May 2024

Traffic Lights will be switched off from 10 am today until 2 am Friday, 31st May 2024 in Deansgrange Village.  During this period, the Deansgrange Road / Kill Lane junction will operate under Stop/ Go traffic management. The works will facilitate essential traffic light upgrades. DLRCC sincerely apologises for any additional traffic disruption.


Friday, 17 May 2024:

Deansgrange road images showing work elements completed

1. Works elements completed/ongoing:

  • Stonework to the southern cemetery entrance was completed on 17 May.
  • Footpath and kerbing work adjacent to Brookville Park/ Springhill junction is 100% complete.
  • Utility and paving works on Kill Lane are ongoing.
  • Kerbing and footpath works at the entrance to Supervalu were completed.
  • Topsoiling of verges was completed


2. Works lookahead:

  • New public lighting to be switched on at the Northern Cemetery Entrance
  • Utility and footpath work along Kill Lane to continue until the end of May.
  • Finish tarmacadam work at Brookville Park/ Springhill junction. Scheduled for Wed 22 May
  • Tarmacadam work at the junction of Deansgrange Road / St. Fintan’s Villas
  • Complete wiring and ducting for traffic signal poles at Kill Lane/ Deansgrange Road junction


3. Early warning items:

  • Traffic Lights switchouts will occur at the junction of Kill Lane / Deansgrange Road on Monday 27th May and Tuesday 28th May to facilitate the installation of new traffic signals and wiring. The junction will be operated by Stop/ Go temporary traffic management. Expect traffic delays
  • The Junction of Kill Lane / Deansgrange Road is scheduled for resurfacing on Monday 10th June and Tuesday 11th June.  This will be evening time work from 9:30 am to midnight.


4. Other:

Next update is on Friday, 31st May 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news



Friday, 03 May 2024:

Deansgrange scheme road work image collage
 

1. Works elements completed/ongoing:

  • An 840m continuous section of two-way cycle track opened on Deansgrange Road on Friday 26th April.
  • Lining and sign marking for the cycle track along Deansgrange Road is 90% complete.  
  • Stonework to the northern cemetery entrance is complete.
  • Road crossings for utility ducting were completed on Kill Lane.
  • Footpath and kerbing work adjacent to Brookville Park/ Springhill junction is 80% complete.
  • A new signalised pedestrian crossing was switched on at Deansgrange Road/ St Fintan’s Villas
  • Utility and paving works on Kill Lane are ongoing.

2. Works lookahead:

  • Continue stonework to the southern cemetery entrance
  • New public lighting to be switched at the Northern Cemetery Entrance
  • Utility and footpath work along Kill Lane to continue until the end of May.
  • Kerbing and footpath works at the entrance to Supervalu
  • Finish Brookville Park/ Springhill junction ( all elements except red tar)
  • We expect the work to be substantially complete by the end of May. Some snagging work will take place during early June.   

3. Early warning items:

  • Works at the junction of Kill Lane / Deansgrange Road will continue to disrupt traffic between 10 am and 4 pm until the end of May.


4. Other: Next update on Friday, 17th May 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news



Friday, 19 April 2024:

Deansgrange road images showing work elements completed

1. Works elements completed/ongoing:

  • Deansgrange road reopened for two-way traffic on Thursday 18th April.
  • The red-coloured cycle track tar along Deansgrange Road is complete.
  • Finishing works the cycle lane will continue for another week before it can be opened.
  • Bus stops along Deansgrange Road are complete.  Buses will resume normal routes next week.
  • Footpath and kerbing works adjacent to Brookville Park/ Springhill junction
  • Utility and paving works on Kill Lane are ongoing.

2. Works lookahead:

  • Signs and line marking along Deansgrange Road.
  • ESB to power up new public lighting and traffic signals outside cemetery entrances
  • Utility and footpath work along Kill Lane to continue until the end of April.
  • New ramp and continuous footpath across Brookville Park/ Springhill junction

3. Early warning items:

  • The works at Brookville Park / Springhill junction will be significant causing more disruption than normal over the next fortnight. Follow traffic management guidance.  

4. Other:

The next update on Friday, 3rd May 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 05 April 2024:

Deansgrange road images showing work elements completed

1. Works elements completed/ongoing:

  • Carriageway resurfacing works are 90% complete along Deansgrange Road.
  • The tarmacadam base course for the red-coloured cycle track is complete.
  • Footpath and utility work in front of Kill O’ the Grange Church was completed during the Easter Holidays.
  • Stonework at the southern and northern cemetery entrances is ongoing.
  • Manhole lids are being lifted and reset in preparation for cycle track surfacing.
  • Bus stops along Deansgrange Road are now complete.

 2. Works lookahead:

  • Cycle track red tarmac surfacing is scheduled for Tuesday 9th April. (Subject to weather conditions)
  • Signs and line marking along Deansgrange Road.
  • ESB to power up new public lighting and traffic signals outside cemetery entrances.
  • Utility and footpath work along Kill Lane to continue until the end of April.
  • Deansgrange Road will reopen for two-way traffic during the week commencing Monday,15th April 2024.

 3. Early warning items:

 4. Other:

Next update is on Friday, 19th April 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 22nd March 2024:

Deansgrange road images showing work elements completed

1. Works elements completed/ongoing:

  • Slipform cycle track kerbing works along Deansgrange Road is complete.
  • Concrete foundations for cemetery entrances are complete.
  • Off-site fabrication of steel railings and stonework is complete.
  • Paving work at the corner of Kill Lane / Deansgrange Road (Grange Pub) (90% complete).
  • Footpath work leading to Springhill is complete.
  • Carriageway resurfacing works have commenced.
  • Traffic lights were installed at the main Deansgrange entrance.
  • Utility ducting along Kill Lane is ongoing.

2. Works lookahead:

  • Finish paving outside Grange Pub.
  • Complete carriageway tarmac resurfacing along Deansgrange Road.  
  • Complete cycle track red tarmac surfacing.
  • ESB Works to power up new public lighting and traffic signals.
  • Works to footpaths outside Kill of the Grange Church to commence after Easter.
  • Utility ducting along Kill Lane to continue.

3. Early warning items:

Since September 2023, we have issued the following notice in DLR Traffic News

"There will be no northbound access to Deansgrange Road from Clonkeen Road / Kill Lane until approximately March 2024"

Unfortunately, the work will overrun. Deansgrange Road will reopen for two-way traffic during the week commencing Monday 15th April, 2 weeks later than scheduled. Works on Kill Lane will continue until the end of April.

4. Other:

Next, updates are on Thursday, 4th April  2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 8th March 2024:

Deansgarnge road images showing work elements completed

1. Works elements completed/ongoing:

  • Footpath and kerbing work along the northern end of Deansgrange Road is ongoing.
  • Completed concrete foundations for cemetery entrances.
  • Off-site fabrication of steel railings and stonework for cemetery piers is ongoing.
  • Kerbing and footpath work at the corner of Kill Lane / Deansgrange Road (Grange Pub) (90% complete)
  • Laid tarmac for new graveyard pedestrian path on 27th February.
  • Excavated trench for new cycle track defender kerb
  • Kerbing works for cycle track defender kerb have commenced

2. Works lookahead:

  • Kerbing and footpath work from Grange Pub to /Clonkeen Park Pedestrian crossing.
  • Progress: Cycle track kerbing along Deansgrange Road is completed.
  • Progress: Tarmac surfacing for the carriageway along Deansgrange Road is completed.
  • Install new traffic signal equipment.
  • ESB Works to power up new public lighting and traffic signals.

3. Early warning items:

Major works on Deansgrange Road over the next fortnight as finishing elements of the scheme progress.

4. Other:

Next, updates on Friday, 22nd March 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 23rd February 2024:

Deansgarnge road images showing work elements completed

 

1. Works elements completed/ongoing:

  • Footpath and kerbing works along the northern end of Deansgrange Road are ongoing.
  • Drainage works along Deansgrange Road are 100% complete 
  • The new traffic light sequence at Kill Lane/ Deansgrange has been road in operation since 12 February
  • Poured concrete foundations for new northern cemetery entrance. (50% complete)
  • Off-site fabrication of steel railings and stonework for cemetery piers is ongoing.
  • Kerbing and footpath work at the corner of Kill Lane / Deansgrange Road (Grange Pub) (75% complete)

2. Works lookahead:

  • Drainage, kerbing and footpath works along Deansgrange Road 
  • Excavate and pour foundations for new Cemetery entrance pillars 
  • Finish kerbing and footpath work at the corner of Kill Lane / Deansgrange Road (Grange Pub)
  • Kerbing and footpath work from Grange Pub to /Clonkeen Park Pedestrian crossing 
  • Excavate and pour new along Deansgrange Road 
  • Complete tarmac for new cemetery footpath 
  • ESB Works to power up new public lighting and traffic signals at the northern cemetery entrance 

3. Early warning items:

Major works on Deansgrange Road on 6 and 7 March during excavation for, and then pouring of concrete cycleway protection kerb. Expect longer than normal traffic delays.

4. Other:

The next work update is on Friday, 8th March 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 09th February 2024:

Deansgrange road images showing work elements completed

1. Works elements completed/ongoing:

  • Construction of loading and parking bays for shops along the southern end of Deansgrange Road is complete.
  • Footpath and kerbing work along the northern end of Deansgrange Road is ongoing.
  • Drainage and utility work is ongoing at Kill Lane ( 60% complete). 
  • Off-site fabrication of steel railings and stonework is ongoing.

 2. Works lookahead:

  • Modifications to traffic signals in Deansgrange Village. This will optimise traffic flows for the next phase of work until March 2024.
  • Drainage, kerbing and footpath work along Deansgrange Road.
  • Excavate and pour foundations for new Cemetery entrance pillars.
  • Kerbing and footpath work at the corner of Kill Lane / Deansgrange Road (Grange Pub).

3. Early warning items:

Two traffic light switchouts will occur in Deansgrange Village in February between 10 am and 4 pm. Stop/Go traffic management will be in operation. At least 5 days’ notice of the specific dates will be given.

4. Other:

The next update on Friday, 23rd February 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 26th January 2024:

Deansgarnge road images showing work elements completed

1. Works elements completed/ongoing:

  • Cemetery footpath: Preparation works for the tarmacadam surface are complete.
  • Drainage works are ongoing opposite St. Fintan’s villas.  
  • Drainage and utility work is ongoing at Kill Lane ( 60% complete). 
  • Off-site fabrication of steel railings and stonework is underway.

 2. Works lookahead:

  • On Monday, January 29th, 2024, the traffic lights in Deansgrange Village will be switched out from 10 am to 4 pm. There will be stop/go traffic management in operation during this time.
  • Construction of loading and parking bays for shops along the southern end of Deansgrange Road will commence on Monday, January 29th.
  • The existing granite pillars at the northern cemetery entrance will be removed.
  • The drainage and kerbing works along Kill Lane will continue.

 3. Early warning items:

Two traffic light switchouts will occur in Deansgrange Village in February between 10 am and 4 pm. Stop/Go traffic management will be in operation. At least 5 days notice will be given regarding the specific dates. 

 4. Other:

We acknowledge that recent traffic light switchouts in Deansgrange Village have caused increased traffic congestion between 10 am and 4 pm. However, we are pleased to inform you that the most disruptive element of the road works is almost over. The contractor made substantial progress during these work periods. As a result, the majority of the future works on Kill Lane can be completed without switching out traffic lights. Moreover, there will be no more traffic light switchouts on Thursdays or Fridays.

 We understand that such traffic congestion can sometimes test people’s patience. While we apologize for any inconvenience caused, we ask for your understanding and patience, particularly towards our traffic management operatives who have marshalled people and vehicles safely through the junction over the last two weeks (some of whom have experienced verbal abuse). Safety is of primary importance, and for this reason, 10 traffic management operatives have been assigned to the junction. They have performed their duties diligently in a testing environment. We ask members of the public to be respectful to workers who are simply doing their job. 

  • Please comply with Stop/Go directions.
  • Please do not distract the traffic management operatives while carrying out their duties.
  • Respect the personal space of traffic management operatives. 
  • Drive carefully through the road works areas.

 

The next, update is on Friday, 9th February 2024. For weekly traffic news updates, please visit https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 19th January 2024:

Deansgarnge road images showing work elements completed

1. Traffic News

  • Ducting and utility works at the junction of Deansgrange Road and Kill Lane will continue between 22nd January to 26th January 2024 from 10 am to 4 pm.  Traffic Lights will be switched off and a Stop/Go traffic management will be in operation at the junction. Weekly traffic news updates are available here https://www.dlrcoco.ie/traffic-management/traffic-news  Next works update on Friday 26th January 2024. 

 

Friday, 12th January 2024:

Deansgrange road images showing work elements completed

1. Works elements completed/ongoing:

  • Kerbing for the cemetery footpath is 95% complete.
  • Parking bay lines were removed and double yellow lines were applied along Deansgrange Road.
  • Utility and drainage works are ongoing at Springhill Park.
  • Traffic Lights were installed at the northern cemetery entrance.

2. Works lookahead:

  • Ducting and utility work at the junction of Deansgrange Road and Kill Lane. As per the early warning notice before Christmas, traffic lights will be switched out in Deansgrange Village from 15th January to 19th January 2024 from 10 am to 4 pm.  Stop/Go traffic management will be in operation.
  • Cemetery footpath. Complete kerbing and path to the underside of the tarmac.
  • Commence loading and parking bays for shops along the southern end of  Deansgrange Road.
  • Move out existing traffic management barriers to prepare space for excavation and installation of cycleway kerb.
  • Stone works to new cemetery entrances to commence.

3. Early warning items: None

4. Other: 

 

Thursday, 21st December 2023:

deansgrange roadworks update

1. Works elements completed/ongoing:

  • Paving works in front of the BYD garage are complete
  • Additional traffic management was provided for December to manage visits to the cemetery
  • Paving works in front of the new Crofter’s Quarter Apartments are 95% complete.
  • Excavation works for the cemetery footpath are 100% complete.

2. Works lookahead:

  • Complete paving works in front of the Crofter’s Quarter
  • New cemetery footpath. Complete kerbing and tarmac surface in January
  • Resume works on Kill Lane in January 2024.
  • Excavation and installation of cycle lane kerb will commence in mid-January
  • Stone works to new cemetery entrances to commence in January.

3. Early warning items: 

  • Parking on Deansgrange Road will be prohibited from 10th January 2024. Leaflets have been distributed to all affected properties, residents and businesses.
  • Traffic light switchouts in Deansgrange Village from 15th January to  19th January 2024. Stop/Go traffic management will be in operation from 10 am to 4 pm.      

4. Other:

 

Friday, 08th December 2023:

Deansgrange road works update 08 Dec 2023

1. Works elements completed/ongoing:

  • Civil engineering works for the pedestrian crossing at the main southern cemetery entrance are 100% complete.
  • Paving works in front of the BYD garage are ongoing and 60% complete
  • Railings and low wall to the northern cemetery entrance have been removed
  • Paving works in front of the new Crofter’s Quarter Apartments are ongoing and 30% complete.
  • Created a gap in the wall for a new pedestrian entrance and walkway at the southern end of the cemetery near Crofter’s Quarter. There will be limited access to a small number of graves between Friday 8th  Dec and Friday 15th Dec when construction works are underway. However, we will continue to facilitate access to graves impacted, by appointment (Monday to Friday 9 am to 5 pm). Email wwinters@dlrcoco.ie to arrange.
  • Signage for an alternative northbound cycle route via Kill Abbey and St. Fintan’s Park is in place.

2. Works lookahead:

  • Complete paving works in front of BYD Garage.
  • Complete paving works in front of the Crofter’s Quarter.
  • Complete the new cemetery footpath to the underside of the tarmac surface.
  • Works on Kill Lane paused for “Operation Open City 2023”.
  • Works on Deansgrange Road shall continue during the month of December.

3. Early warning items: None 

4. Other:

  • Additional Traffic Management is in place for December to facilitate the visiting of graves in the cemetery. The Northern cemetery entrance will be reponed temporarily during working hours.  
  • The next work update is on Friday 5th January 2024. Weekly traffic news updates are available here https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 24th November 2023:

1. Works elements completed/ongoing:

  • Completed Civil engineering works for a new pedestrian crossing at Deansgrange Road / St. Fintan’s Villas.
  • Civil engineering works for the Pedestrian Crossing at the Southern Cemetery Entrance is 50% complete.
  • Completed drainage works in front of the BYD garage.
  • Completed road crossing for drainage over high voltage ESB UG cable on 22 November 2023.  
  • Paving works in front of the BYD garage commenced on 23 November.
  • Commenced demolition of the northern cemetery entrance.

2. Works lookahead:

  • Continue paving works in front of BYD Garage.
  • Complete kerbing works in front of the BYD Garage.
  • Upkeep of traffic management diversions.
  • Works on Kill Ave until 1 December, then paused for “Operation Open City 2023”.
  • Works on Deansgrange Road shall continue during December.

3. Early warning items: None

4. Other:

Additional Traffic Management will be in place for December to facilitate visiting of graves in the cemetery. The Northern cemetery entrance will be reponed temporarily during working hours.  

A traffic survey is underway in the Foxrock Ave/ Hollypark area to measure current traffic volumes.

The next work update is on Friday 8th December. Weekly traffic news updates are available here https://www.dlrcoco.ie/traffic-management/traffic-news.

5. For Images of the above updates kindly see the "Gallery" icon above or at the bottom of this page.

 

Friday, 10th November 2023:

1. Works elements completed/ongoing:

  • Kill Lane road widening works completed during school mid-term break. 
  • Utility work is ongoing to create a new pedestrian crossing at Deansgrange Road / St. Fintan’s Villas.
  • Drainage works in front of the BYD garage are 90% complete.
  • Excavation work in preparation for new paving in front of the BYD garage is complete.

Deansgrane roadworks update 10th Nov 2023

 

2. Works lookahead:

  • Finish drainage works in front of BYD Garage and prepare for paving crews. New road crossing in front of BYD Garage on Monday 13 Nov . Liaison with ESB to ensure safe excavation adjacent to high voltage underground line.
  • Continue works for a new pedestrian crossing at Deansgrange Road / St. Fintan’s villas. Ducting, service chambers and traffic signal infrastructure.
  • Kerbing works in front of the BYD Garage. Delivery of paving materials
  • Upkeep of traffic management diversions.

 

3. Early warning items: None

 

4. Other: The next work update is on Friday 24th November. Weekly traffic news updates are available here https://www.dlrcoco.ie/traffic-management/traffic-news

 

Friday, 27th October 2023:

1. Works elements completed/ongoing:

  • Drainage pipes work approx. 80% completed.
  • The Footpath kerb works approx. 30% completed.
  • 25% of works to 3 pedestrian crossings completed.
  • Temporary traffic management works competed to install temporary traffic signals.
  • Drainage pipe survey works completed.

 Construction work on Deansgrange road

2. Works lookahead:

During the mid-term break, work will take place on Kill Lane outside the entrance to the school/church. Works involve widening and reinstating the cycle facilitate.

3. Early warning items: None

4. Other: Works were carried out on Kill Lane to install bollards along the bus lane to restrict vehicles queuing into the bus lane

 

Friday, 20th October 2023:

1. Works elements completed / ongoing:

  • Installation of bus kerbs to provide accessible bus stops.
  • Excavation for new drainage system
  • Installation of new gullies with 3m deep connections
  • Ongoing liaison with utility companies to ensure safe excavations.

Deangrange road work images

2. Works lookahead:

  • Ducting, service chambers and traffic signal infrastructure for pedestrian crossings
  • Continue all drainage works.
  • Kerbs and footpath work.

Deansgrage road works update trench for new drainage image.

3. Other works:

  • Additional traffic management signage to assist with diversion routes to be installed.
  • On Thursday the 19th of October there was an issue with the traffic signals at the Deansgrange crossroads junction. There was a cable issue resulting in the signals being off for several hours this issue has since been resolved.
  • There is an ongoing issue with Google Maps incorrectly representing Deansgrange Road as being closed. We have been in contact with Google Maps to resolve it.

 

 4. Early Warning issues: Works are planned for Kill Lane during the school mid-term.

 

Friday, 13th October 2023:

1. Works elements completed:

  • Work items with long lead-in times are being ordered e.g. Granite and railings for new cemetery entrances.
  • Construction of new gullies. In some cases, excavations were 3m deep to connect to surface water drains. Despite this, the works have progressed well.

Deansgarnge road images showing work elements completed

Deansgrange road new drainage work 3

 

2. Works elements ongoing:

  • Ducting, service chambers and traffic signal infrastructure for new pedestrian crossings.
  • Kerbs and footpath works.  

Densgrange road work elements on going

3. Works lookahead: 

  • Kerbs and footpath works to continue
  • Ducting, service chambers and traffic signal infrastructure to continue
  • Upgrade of drainage pipes to alleviate recurrent pluvial flooding issue at Deansgrange Village to commence

4. Communication activities completed:

  • Liaison with local schools to arrange work on Kill Lane during the mid-term break
  • Ongoing liaison with utility companies to ensure safe excavations
  • Ongoing liaison with Traffic light signal control centre and Gardai
  • Meetings with public/businesses by Circet and DLR, >10 formal meetings to date plus normal day-to-day meetings
  • DLR contacted Google Maps to resolve an issue where the one-way system was incorrectly represented.

5. Mitigation works completed:

  • New yellow box and line marking at Deansgrange Village
  • New Yellow box at St Fintan’s Villas
  • Additional traffic management signs provided

Deangrange road mitigation work completed

 

 

 

 

 

 

 

 

 

6. Early warning items:

  • Works are planned for Kill Lane during the school mid-term

7. Other:

  • Ongoing review of traffic management installation to ensure correct signage is in place and easily understood. There have been reports of people ignoring the signs and travelling incorrectly against traffic management instructions. This is being reviewed on an ongoing basis and appropriate measures are being installed
  • We are considering the installation of a 30kph road works speed limit along the road

 

Thursday, 28th September 2023: Construction works are well underway. New drainage gullies and kerbing works have commenced. The new one-way system is in operation. We are working with all stakeholders to optimise the system and ensure it operates as efficiently as possible for all road users.

Monday, 11th September 2023: Circet has been appointed as the contractor for this scheme. They have mobilised onsite and commenced site investigation works. They will be installing a one-way system on Deansgrange Road between St. Fintans Villas and Kill Lane on Monday the 18th of September to facilitate the works.

Friday, 8th September 2023: The public consultation for this scheme closed on 27 October 2022.DLR has reviewed all the feedback and comments received. The Chief Executive’s Report on the Public Consultation was brought to the Elected Members. The report and its recommendations were noted by Councillors and amended by resolution at the Dún Laoghaire Rathdown County Council meeting on 13 March 2023.

The Consultation Report, EIA & AA Screening Report Addendum, Amended drawings and Deansgrange FAQs are available to read here: Active Travel Improvements: Deansgrange Cycle Route Scheme 

 

Background

Deansgrange cycle route scheme proposed project

The Dún Laoghaire-Rathdown County Council (DLR) Active School Travel project is centred on the concept of providing a connected and safe network of walking and cycling routes to schools across the county, and this concept has been emphasised from project inception in August 2020.

The Sea to Mountains route will link east to west across the County. Starting at Blackrock Dart Station, crossing the N11 to Deerpark. It will then continue south linking to the Sandyford Cycle Route and Kilmacud Luas Stop and on to the Slang River Greenway and Wicklow Way.

The Park to Park route will link north to south across the county. Starting at the coast at Blackrock Dart Station and then joining the existing pathways in Rockfield Park. From there it will continue south along Deansgrange Road linking to the Loughlinstown to Deansgrange Greenway and ending by linking south to the coast.

The Mountains to Metals route will link east-west across the county. Starting at the Sandyford Cycle Route, linking to the Sea to Mountains Route, the route also links up to the Park to Park route, north through residential areas and new developments and on to the Metals.

The proposed routes aim to connect quiet residential streets with existing safe walking and cycling infrastructure, to create a joined-up network.

Need for this project:

Dublin is the 17th most congested city in the world. Car ownership levels in Ireland have risen exponentially over the last 30 years.

Data showing car ownership levels in Ireland have risen exponentially over the last 30 years

(Source: CSO)

No new roads are being built to keep up with this increased demand and there are no options to increase traffic capacity on the existing roads. This means that congestion levels will continue to deteriorate if alternatives are not provided. Both local and national policies are directing that we reduce C02 emissions by half in the next 7 years. This means that almost half of the current car trips need to be converted to sustainable traffic trips to meet these objectives. The Bus Connects plan is proposing high-quality public transport for DLR which will provide improved public transport. For other areas, a high-quality walking and cycling network is required.

Current Project Status:

Over the last 3 years, DLR has been implementing the Active School Travel network. The last remaining section to be completed is Deansgrange Road. During this time DLR had proposed a variety of different design options for Deansgrange Road. There has been a series of public engagements both statutory and non-statutory. In March 2023 the Elected Members of DLR voted to approve a scheme on Deansgrange Road that provides for two-way traffic and two-way cycling on the road. This design requires the removal of public parking along Deansgrange Road.

For more info about the scheme objectives, visit Active Travel: Deansgrange Cycle Route Scheme 

FAQs

1. Where can I see information relating to the consultation for this scheme?
Information relating to the Part 8 process for this scheme is
available here: Active Travel Improvements: Deansgrange Cycle Route Scheme - Dún Laoghaire-Rathdown County Council - Citizen Space

2. How long will the works take?
The works are programmed to take approximately eight months. 

3. Why is a one-way system traffic management plan being used?
The provision of the cycle facility requires a new concrete kerb at the edge of the car lanes. This will require a trench to be dug along Deansgrange Road and the kerb poured into the trench. The trench needs to be wider than the kerb to facilitate the machine access and extra space is required to allow safe space for workers. This leaves insufficient space to maintain
two-way traffic (even if the parking is removed). 

4. Why don’t you use stop / go?
The use of a stop/go set-up would result in more significant congestion in this area.
For example, if the section of Deansgrange Road was done in 100m sections using a stop/go system this would usually take 3-5mins between ‘go’ cycles. The junction at Deansgrange Road typically cycles every 2 mins. This means that there would be two changes of the lights at the junction before you get a ‘go’ at the stop/go system. This would quickly backlog traffic in both directions on Deansgrange Road. The use of stop/go would also not resolve the issue around having to keep the trench for the kerb open until the kerb is poured. The use of stop/go would also require the removal of parking on Deansgrange Road once set up. The provision of a one-way system allows for the retention of parking for a longer period of time.

5. What is the extent of the one-way system?
The one-way system will be installed on Deansgrange Road south of St Fintan’s Villas and
continuing up to the junction with Kill Lane. The section between St Fintans Villas and the Rowanbyrn junction will be done as a subsequent traffic management phase.

deansgrange FAQ map image

6. What are the diversion routes?
Vehicles travelling north on the N11 will be diverted initially via Johnstown Road / Pottery Road. For vehicles that continue past this junction, they will be diverted via the N11 – Newtownpark Ave. Vehicles approaching the works from Clonkeen Road will be diverted left
via the N11. 

7. Will this mean a lot of additional traffic locally?
Data collection noted that 75% of the northbound traffic on Deansgrange Road drives through the area. This means that 75% of the existing traffic starts and ends their journeys outside these areas. If these vehicles follow the signed diversion route this will result in less traffic in this area. 

8. Are the 84 and 84a buses impacted?
Yes, the northbound bus service is diverted via Abbey Road for the duration of the works:

deangrange faq


The bus will stop at the bus stops along the diversion route. There are bus stops on Kill Lane close to the NCT centre here: https://www.google.com/maps/@53.2793962,-6.1621844,3a,75y,35.07h,85.98t/data=!3m6!1e1!3m4!1sN7uyyrMRdWc4hDlL3BShow!2e0!7i16384!8i8192?entry=ttu
 

9. Why didn’t DLR provide cycle tracks on Abbey Road instead?
Abbey Road is part of the proposed cycle network and requires high-quality facilities in addition to Deansgrange Road. A network of cycle routes is required to provide sustainable options for users. 

10. 
I live in the following area, how does the one-way system affect me:

St Fintans Park / Villas: These exits onto Deansgrange Road are outside the one-way system so movements are unrestricted. When exiting onto Deansgrange Road you will be permitted to turn left and right. When returning via Deansgrange Road you must enter via the northern end.


Brookville Park / Grange Grove: These exits onto Deansgrange Road are outside the one-way system so movements are unrestricted. When exiting onto Deansgrange Road you will be permitted to turn left and right. When returning via Deansgrange Road you must enter via the northern end.


Grange Terrace: You must enter Deansgrange Road from the northern end and exit through the one-way system.


Deansgrange Cemetery: You must enter Deansgrange Road from the northern end and exit through the one-way system. In addition, the northern entrance to the Cemetery will be closed for the duration of the works. Vehicular access to the cemetery will be via the main entrance. This has been communicated to the funeral directors.


Kill Lane area east of Deansgrange Road: There is an existing no-right turn ban at this location so access is unchanged.


Kill Lane area west of Deansgrange Road: There are two diversion options for local residents, via the N11 / Newtownpark Ave via Kill Lane / Abbey Road


Clonkeen Road Area: There are two diversion options for local residents via the N11 / Newtownpark Ave or via Kill Lane / Abbey Road

 

11. I am a pedestrian, how will traffic management affect me?
Pedestrian access will be maintained throughout the works


13. I am a pedestrian or cyclist who uses the cemetery. Will this be still available?
Yes, pedestrian and cycle access is maintained but the northern entrance will be restricted. The pedestrian/cycle and vehicular gates at the tea rooms will be available. Signage will be provided directing people to the alternative routes.
  

14. I am a cyclist how will traffic management affect me?
Cyclists' access to Deansgrange Road northbound will be diverted for the duration of the one-way system similar to the vehicular traffic. 


 

15. I have a query related to the construction works who do I contact?
Contacts:

 

We care about your feedback. Have your say.

Is this page useful?

Any concerns with your local area?

Report a problem with the Council