Travel & Transport

Temporary Closure of N11 between its junction with Kill Lane (Foxrock Church) to on ramp R118 Cherrywood interchange southbound and northbound

General News

Referring to Section 75 of the roads Act, 1993.  Dún Laoghaire-Rathdown County Council has approved an application from Roadstone, Fortunestown, Belgard, Tallaght, Dublin 24 to temporarily close part of the N11 Stillorgan Road between its junction with Kill Lane (Foxrock Church) to on ramp R118 Cherrywood Interchange junction southbound and northbound from Monday 22nd January, 2024 to Sunday 30th June, 2024 between 19:30 hours to 05:00 hours each day. 

The start time of 1930hrs is required as it allows the Contractor sufficient time to carry out the section of the works that creates the most noise i.e. the planing of the existing road surface.   

 

It is a requirement that this section of the works is completed by 2300hrs, therefore commencing the works at a time past 1930hrs would serve to severely limit production and have a detrimental effect of the programme of the overall works. 

An earlier time than 1930hrs would assist with the programme but the effect on traffic movements would not be manageable, as such it is seen that a 1930hrs start time provides the best approach in balancing both traffic movements and ensuring progress of the works. 

A Traffic Management Plan will be in operation and pedestrian, local access and access for bus and emergency services will be maintained at all times.  Diversion routes will be clearly signposted. 

 

The purpose of the closure is to allow for realignment of the traffic lanes.

News

View all

We care about your feedback. Have your say.

Is this page useful?

Any concerns with your local area?

Report a problem with the Council